Geller's and Meadow Ridge Area Sewer Improvements

Project Purpose:

The reason for the improvements is to reroute the existing sanitary sewer force main from existing sanitary lift station SA-11 to avoid the Brookwood area, reroute the existing gravity sanitary sewer that services the Geller’s area with a new lift station to avoid the Brookwood area, modifying existing sanitary lift stations SA-11 and SA-47 to accommodate the change in flow due to this rerouting, and moving the location of the existing compost site. 

Project Improvements:

Sanitary Sewer Improvement District No. 1319 will involve the construction of improvements consisting of storm sewer, water mains, gravity sanitary sewer, sanitary sewer force main installed via directional drill and/or open cut, concrete streets, curb and gutter, sidewalks, sanitary sewer lift station, sanitary sewer lift station modifications, asphalt pavement, and other miscellaneous installations. Also included in the project is the reconstruction of the Ninth Street E. and First Avenue E. intersection and utilities, which are paid for with City funds. 

Project Costs:

Project Timeline:

  • Project begin: September 2018
  • Project end: November 2018
  • Project complete: 75%

Road Closure:

Ninth Street E and First Avenue E intersection closure

  • Intersection of First Avenue E. and Ninth Street E. closed Sept. 4-Oct. 17 for repairs

Completed Work:

  • Storm sewer
  • Water main

Current Work:

  • Force main
  • Compost site
  • Lifts
  • Ninth Street E. intersection
  • SA 9
  • SA 48 excavation
  • SA 11 bypass installation and coating preparation

Upcoming Work:

  • SA 48 structure installation
  • Compost site fence
  • Signs
  • SA 11 coating