First Ave. E. Reconstruction (Fourth St. E. to Ninth St. E.) - District No. 3001

About this Project

This infrastructure replacement project will consist of a full reconstruction of First Avenue East from Fourth Street East to Ninth Street East, Fourth Street East from Main Avenue to First Avenue East, and Fifth Street East from Main Avenue to First Avenue East. 

We will remove existing water mains, sanitary sewer, streets, and street lights and install new water mains, sanitary sewer, storm sewer, concrete streets, and street lights. Sidewalks will be replaced as needed throughout the project area.

Estimated Construction Cost

Project Schedule

  • Estimated Begin: May 2017
  • Estimated End: June 2018
  • Project complete: 98%

Road Closures

  • Westbound 1st Avenue traffic shifted west
  • Intermittent work remaining in right-of-way

Completed Work

  • Water main
  • Sanitary sewer
  • Storm sewer
  • Paving
  • Light base
  • Sidewalk
  • Striping
  • Flatwork

Current Work

  • Curb pain
  • Parking stall striping
  • Street patches
  • Miscellaneous sidewalk repair

Upcoming Work

  • Punchlist