Eighth Ave. NW and 26th St. NW Paving - District No. 2240

About the Project


This multi-phase project involves utilities, a storm water retention pond, and paving. The project will include paving of Eighth Avenue NW from Ninth Street W. to 26th Street NW, as well as the reconstruction and paving of 26th Street NW from Eighth Avenue W. to First Avenue NW. 

Estimated Construction Costs


  • $3.1 million

Project Schedule


  • Begin Date: October 2017
  • End Date: October 2018
  • Project Complete: 99%

Road Closures

  • Eighth Avenue W. open to local traffic
  • 26th Street NW closed at BNSF crossing

Completed Work

  • All underground utilities
  • West Fargo Fifth Addition
  • Embankment
  • Lift forcemain
  • Ponds pumped
  • Gravel shoulders
  • Dirt work
  • Seeding
  • Street lights
  • 26th Street NW railroad crossing

Current Work


  • Seeding and mulching
  • Pumping down Kost Butler System continues through Nov. 7

Upcoming Work


  • Waiting on 404 and 408 permit for outfall installation
  • Stabilization