Eighth Ave. NW and 26th St. NW Paving - District No. 2240

About the Project


This multi-phase project involves utilities, a storm water retention pond, and paving. The project will include paving of Eighth Avenue NW from Ninth Street W. to 26th Street NW, as well as the reconstruction and paving of 26th Street NW from Eighth Avenue W. to First Avenue NW. 

Estimated Construction Costs


  • $3.1 million

Project Schedule


  • Begin Date: October 2017
  • End Date: October 2018
  • Project Complete: 99%

Road Closures


  • Eighth Avenue W. open to local traffic only
  • BNSF crossing installation will require 26th Avenue NW closure (not yet scheduled)

Completed Work

  • Gravel shoulders
  • Dirtwork
  • Seeding
  • Streetlights

Current Work


  • Meeting with BNSF to discuss crossing installation

Upcoming Work


  • 26th Avenue NW railroad crossing installation