13th Ave. E. and Ninth St. E. Intersection Improvements - District No. 2243

Ninth St E and 13th Ave E Intersection Improvement

Ninth Street E. Street Level Looking South
Ninth Street E. Street Level Looking North
Intersection of Ninth St. E. and 13th Ave. E. Looking Southeast
Intersection of Ninth St. E. and 13th Ave. E. Looking Northwest
Intersection of Ninth St. E. and 13th Ave. E. Looking Northeast
Intersection of Ninth Street E. and Seventh Ave. E. Looking Northwest

About this Project


The project consists of reconstructing and widening the 13th Avenue E. and Ninth Street E. intersection to accommodate dual left turn lanes in all directions. The project will also involve the addition of a northbound through lane from 13th Avenue E. to Seventh Avenue E., and upgrades to outdated/undersized utilities within project limits to minimize future disruptions.

Estimated Construction Cost


  • $5.5 million

Estimated Special Assessments

Project Schedule


  • Begin Date: August 2017
  • Estimated End Date: August 2018
  • Percent Complete: 95%

Road Closures: Phase 3

Phase 3 Traffic Control Map
Ninth Street. E. and 13th Avenue E. Intersection Improvement Phase 3 Traffic Control
Road Closures
  • Median closed from 14th Avenue E. to 10th Avenue E.
  • Traffic control scheduled for removal week of July 16

Completed Work 

  • 13th Avenue E.: Utilities and road
  • Ninth Street E:
    • North- and southbound main line paved
    • Utilities
    • Road
    • Sidewalk
    • Turn lanes
    • Street lights

Current Work

  • Ninth Street E. striping and signing
  • Ninth Street E. seeding
  • Retaining wall installation
  • Sidewalk at utility locations